Please be advised that a temporary asphalt path will be installed between the East Gate Loop and the southeast stairs leading to the Brody Learning Commons Plaza on Thursday, Sept. 11, from 7 a.m. to 7 p.m.
Scope of work:
- Removal of existing wood chip surface along the current pedestrian path
- Installation of a new 6-feet-wide temporary asphalt path from the East Gate Loop to the southeast BLC stairs
Paths impacted:
- The wood chip pathway will be closed to pedestrians during installation
- A detour route will be posted redirecting pedestrians to the BLC stairs
- ADA pathway adjacent to the work area will remain open and unobstructed
Safety measures:
- Detour signage will be installed at the Beach side of the pedestrian pathway
- Flaggers will be posted along the work zone to redirect pedestrian traffic
- Work zone will be clearly marked with appropriate barriers and fencing