From Jan. 6 to Jan. 17, scaffolding will be constructed around Remsen Hall as part of the Dormer Replacement Project. Materials will be carted from Bowman Drive to an area on the west side of Remsen Hall. Deliveries will be completed from 5:30 to 7 a.m. to avoid traffic impacts. During construction of the scaffolding, some entrances/exits and pathways around the building may be temporarily unavailable, and alternate routes will need to be used. Once the scaffolding is built, it will remain in place through March.
The logistics plan is here.
Contact Mike Gourley at 443-676-2050 or mgourle3@jhu.edu with any questions.