ADA repairs to begin on Homewood campus

The JHU Homewood campus will begin a series of ADA repairs to various pathways on campus. Please be advised that part of the pathway in front of Hodson Hall will be closed for ADA paving repairs beginning March 16; the work is expected to be completed by March 21, weather permitting. The path from the ADA parking lot behind Clark Hall will be closed beginning March 22, followed by repairs to Ames Hall (tentative start date of March 29). JHFRE Design and Construction will keep everyone updated as we progress throughout the campus with the ADA repairs.

Click here for more information and the logistics plan.

If you have questions or concerns, contact Brandon Benjamin, senior project manager, at bbenjamin@jhu.edu.