Hoist on top of McCoy Hall for Tankless Conversion Project

JHFRE Design and Construction will be relocating the hoist from the roof of Homewood to McCoy Hall for the Tankless Conversion Project. The hoist will be used to bring materials to the penthouse mechanical room and remove construction debris. It will be in operation Jan. 5–20. The service driveway will be blocked for the delivery of equipment and hoisting on Tuesday, Jan. 10, and Wednesday, Jan. 11. The delivery trucks will pull into the driveway off St. Paul Street.

The logistics map is on the Facilities and Real Estate website.

If you have questions or concerns, contact Brandon Benjamin at bbenjamin@jhu.edu.